30 Apr Willmott Dixon masters on-site social distancing
Willmott Dixon give an example of where using technology and new working practice it was able to keep its £48m Birmingham University school of engineering project on track during the coronavirus epidemic.
Nick Proverbs, senior operations manager, said the project had now successfully adapted to ensure workers could observe social distancing measures.
The change has involved clearer planning of activity and in some instances moving work off-site to give workers more space.
Now the construction firm also holds virtual site tours for its client.
“When guidance by Construction Leadership Council was released, our first action was to review what roles could be performed from home, which led to our design and commercial teams relocating to their homes,” said Proverbs.
“This helped free up space in our site cabins to implement social distancing measures, placing each desk station more than 2m apart at any one point.
“Our supply chain partners also implemented the same process in their site cabins to reduce the number of people to just key roles.”
Site team re-configured operations to ensure social distancing site lay-out.
Willmott Dixon looked at where bottlenecks were likely to be, such as staircases and routes in and out of the site.
To combat this, it created a series of one-way systems, allowing site operatives to keep their distance and avoid oncoming people.
To give site operatives greater space to take their breaks in, Willmott Dixon hired a 190 sq m marquee, erected on one of the University car parks.
In other areas, Willmott Dixon created rotas and removed seats to prevent overcrowding.
The firm has also appointed a site attendant to monitor the drying room to ensure no more than two people use it at any one time.
Canteens, meeting rooms, desks, and all site entrances and exits have been equipped with hand sanitisers.
Each morning, Willmott Dixon holds toolbox talks with staff and supply chain partners to communicate the latest guidance and working practices.
Meetings are held in open areas, allowing for the maintenance of the 2m rule.
Where roles can abide by social distancing work has continued. For roles such as installing plasterboard, where it is near-impossible to work safely while abiding by social distancing, work has stopped.
Proverbs said that if anyone shows symptoms of the coronavirus or needs to self-isolate, they are empowered to do so and it is critical they abide by this directive.
Willmott Dixon has finished constructing the concrete frame and is currently building the atrium roof, external windows and cladding, as well as internal stud partitioning and mechanical and electrical installations.
“Most of the work has been able to continue and abide by social distancing,” said Proverbs.